Ashoka Buildcon’s joint venture with SAM India has been declared the lowest bidder for two Jaipur Metro Phase-II packages. The combined quoted engineering, procurement and construction price is Rs2,758.31 crore, including GST, according to the company’s November 20, 2026 exchange filing.
Ashoka is the lead member of the ABL-SAM India JV. The announcement is an L1 declaration for projects of Rajasthan Metro Rail Corporation Limited, not confirmation that a final contract has been awarded or that construction has started.
Two packages, one combined quoted figure
Package 3 carries a quoted price of Rs1,130.31 crore, including GST. Its scope covers the design and construction of an elevated viaduct and 12 elevated stations, including architectural finishing, under Jaipur Metro Phase-II MRTS.
Package 4 has a quoted price of Rs1,628 crore, including GST. It includes an elevated viaduct and 11 elevated stations with architectural finishing, modification of part of the operational Phase-I corridor and construction of the Khasa Kothi Phase-I station.
The two package prices add up to the disclosed Rs2,758.31 crore. That is the JV’s combined quoted project value, inclusive of tax. The filing does not specify Ashoka’s percentage participation or allocate that total between Ashoka and SAM India.
What L1 tells readers, and what it does not
L1 identifies the lowest-bid stage. It is a meaningful procurement milestone, but it should not be substituted for a final award announcement. The operative statement in the filing is that the JV has been declared the lowest bidder for the two projects.
Being named lead member does not, by itself, establish that the entire quoted value belongs to Ashoka. Without the participation split, treating Rs2,758.31 crore as Ashoka’s standalone order value would go beyond what this disclosure provides.
Nor is a quoted EPC price the same thing as recognised revenue, cash received or profit. The announcement does not quantify a margin or an earnings contribution from these packages.
Execution terms to keep separate from commencement
The annexure describes each package on a lump-sum basis with a 36-month execution period and a 12-month defect liability period. Those are the disclosed project terms, not evidence that a construction clock has already started on November 20.
For now, the verified development is the JV’s lowest-bidder position. Readers tracking the next stage should distinguish a subsequent award or execution update from this bid-stage announcement, while checking whether any later disclosure explains Ashoka’s share of the work.
Source: Ashoka Buildcon’s 20 November 2026 exchange filing and Annexure I.
Source basis: Ashoka Buildcon’s November 20, 2026 exchange disclosure and its project annexure. The poster is an original conceptual illustration, not a photograph of the proposed works. This report explains a company announcement and is not an investment recommendation.
Follow Stockmarket360