SJVN has reported the foundation-stone ceremony for its 669 MW Lower Arun hydroelectric project in Nepal. The November 23, 2026 exchange filing puts the estimated project cost at Rs5,792.36 crore and the commissioning target in financial year 2030-31.
The milestone is project development, not the addition of 669 MW of operating capacity today. The company says major construction packages have been awarded and construction activities are underway. Its stated commissioning target remains ahead.
The project behind the headline
Lower Arun is being developed on the Arun River in Nepal’s Sankhuwasabha and Bhojpur districts by SJVN Lower Arun Power Development Company, a wholly owned SJVN subsidiary. The project is structured on a Build, Own, Operate and Transfer basis.
The plan comprises four generating units of 167.25 MW each, a 17.4-kilometre head race tunnel and a surface powerhouse. SJVN says it is designed to work in tandem with its upstream 900 MW Arun-3 project: water discharged from Arun-3 would be used again for generation at Lower Arun, without constructing a separate storage reservoir.
Keep capacity, output and tariff separate
The 669 MW figure describes the project’s planned generating capacity. SJVN separately envisages approximately 2,901 million units of annual energy generation and gives a tentative tariff of Rs4.99 per unit. These are different measures, and the filing labels the tariff tentative.
The release also says 21% of generated energy will be supplied free to the Government of Nepal under the Project Development Agreement. Multiplying the whole projected annual generation by the tentative tariff would therefore not establish SJVN’s eventual revenue or profit. The release does not provide a project earnings forecast.
A ceremony is not commissioning
SJVN says the foundation stone was jointly laid by the Prime Ministers of India and Nepal through a virtual ceremony from New Delhi. It is a visible development milestone, but it does not show that the units are commissioned, producing the projected annual energy or earning the tentative tariff.
The Rs5,792.36 crore number is an estimated project cost, not an order win or reported revenue. Likewise, FY2030-31 is the company’s commissioning target, not a confirmation of completed delivery. Future construction and commissioning disclosures will be the evidence to track against that target.
The practical reading is to keep the stages distinct: foundation stone, construction and eventual commissioning. The filing supports progress on a large cross-border hydro project, without turning its future capacity, output or tariff assumptions into present operating results or a share-price promise.
Source: SJVN’s November 23, 2026 exchange filing and full attached press release.
The poster is an original conceptual Himalayan hydro-project illustration, not a photograph or engineering rendering of Lower Arun.
Disclaimer
This article is for information and education only and is based on public sources. Please double-check the original source before making any financial decision. We hold no shares in the companies mentioned. Our purpose is to promote financial literacy and resources, without any personal or monetary motive. We have never taken or built trading or investing positions to spread false price information for personal gain. We have not used, and will not use, this platform to mislead any trader or investor. This is not investment advice.