ACME Solar Holdings has commissioned 57.69 MW of contracted firm and dispatchable renewable energy capacity through its wholly owned subsidiary, ACME Sigma Urja. The company dates the commissioning to November 19, 2026, while specifying November 21 as the commercial operation date for this tranche.
The disclosure concerns part of a 250 MW contracted FDRE project at Kharnai village, Rawatbhata tehsil, in Rajasthan’s Chittorgarh district. It is a tranche milestone, not an announcement that the entire 250 MW contracted project has reached commercial operation.
Three capacity figures describe different components
The commissioned tranche comprises 100.02 MW of installed solar capacity alongside a battery energy storage system rated at 57.69 MW and 265.38 MWh. The filing separately identifies 57.69 MW as the commissioned FDRE contracted capacity.
These figures should not be added together and presented as a larger contracted supply figure. The solar installation, battery power rating, battery energy capacity and contracted FDRE capacity describe different aspects of the same disclosed tranche. MW and MWh are also different units, not interchangeable measures.
Commissioning and the commercial date are separate
ACME states that commissioning took place on November 19, with commercial operation scheduled for November 21. Reporting the commercial milestone as already achieved on November 19 would collapse two dates that the company explicitly separates.
The project is connected to the Neemuch Pooling Station, and its power purchase agreement has been signed with NHPC. The announcement does not provide the PPA tariff, this tranche’s investment cost or an earnings contribution, so it does not support a revenue or profit forecast.
This is the Sigma Urja project, not the earlier battery tranche
Readers following ACME’s recent updates should distinguish this Kharnai project from the earlier ACME Greentech Seventh battery commissioning report. The current disclosure names ACME Sigma Urja, a different subsidiary, and a 250 MW contracted project with an NHPC agreement.
The next useful confirmation would be an update on commercial operation and subsequent project progress. For now, the company’s stated milestone is a 57.69 MW contracted FDRE tranche commissioned on November 19, with November 21 specified for commercial operation, not completion of the whole project or a quantified financial benefit.
Source: ACME Solar Holdings exchange filing dated November 19, 2026.