Diamond Power Infrastructure has received a conductor supply order from Adani Energy Solutions for the Bhadla-Fatehpur high-voltage direct current transmission project. Its November 19, 2026 exchange filing puts the purchase order at Rs707.80 crore including GST, with a basic value of Rs599.83 crore excluding GST.
The distinction matters because the larger headline figure includes tax. It is also a value at specified commodity and currency benchmarks, rather than a promise that the final billing will remain unchanged. The filing describes variable pricing linked to aluminium and the rupee-dollar exchange rate.
A supply order, not the entire transmission project
The detailed annexure specifies 8,948.33 km of AL-59 Lapwing conductors and 111 km of AL-59 Moose conductors, totalling 9,059.33 km. Those are conductor quantities. They should not be read as the length of the transmission corridor itself.
The purchase order covers design, engineering, manufacture, testing, packing and supply on a Delivered at Place basis for the plus-or-minus 800 kV HVDC line. Diamond Power is supplying conductors, not announcing that it has won the entire Bhadla-Fatehpur project or that the line has been commissioned.
Diamond Power describes the order as its entry into the HVDC transmission segment. That is the company’s stated business milestone. The disclosure does not establish completed deliveries, recognised revenue or profit from this order.
Why the final order value can move
The stated value uses base indices of LME aluminium at US$2,550 per metric tonne, a premium of US$106 per metric tonne and a rupee-dollar exchange rate of 87. These are contract pricing references, not a statement of current market prices.
For each month’s supplies, the filing says the final price will follow a variation formula using average LME aluminium prices and the exchange rate for the month before scheduled dispatch. Aluminium and currency movements are therefore passed through under the disclosed mechanism.
The company says it does not carry aluminium price or currency risk beyond the pricing period. That statement should not be expanded into a claim that the order has no risk at all. The announcement does not quantify margins or guarantee the financial outcome.
Deliveries extend to December 2027
Supplies are scheduled month by month according to project requirements, with completion on or before December 31, 2027. The disclosed terms include performance security through a corporate guarantee and an 18-month defect liability period applied lot by lot. Diamond Power says the domestic order is not a related-party transaction and its promoter group has no interest in the awarding entity.
The filing establishes receipt of a purchase order on November 19. The next execution milestones are manufacture, dispatch and delivery under that schedule. For readers assessing the announcement, the useful separation is between the tax-inclusive headline, the basic value, the variable pricing mechanism and the delivery obligations still ahead.