Leapfrog Engineering Services has received a letter of intent from Karnataka Power Transmission Corporation Limited for a contract valued at Rs22.05 crore, excluding GST. Its November 21, 2026 exchange filing describes materials and equipment supply, erection and civil works. It does not report completed execution or revenue earned.
What the amount covers
The precise amount disclosed is Rs22,05,03,082.69. The rounded Rs22.05 crore headline therefore refers to the contract value before GST, not a tax-inclusive total. The filing gives one combined value for the stated scope; it does not provide separate amounts for supplies, erection and civil works.
Materials and equipment include mandatory spares. The erection portion includes testing and commissioning. Civil works form the third part of the scope. These descriptions identify the work covered, but they do not establish that equipment has been delivered, installed or commissioned.
Keep the letter-of-intent stage visible
The company’s stated milestone is receipt of a letter of intent, or LOI, from KPTCL for award of a contract. That is the stage this report describes. The short disclosure does not separately announce a signed definitive agreement, a notice to begin work or completion of the project.
Those distinctions matter when reading an order headline. A stated contract value is not, by itself, a record of sales already booked, cash collected or profit generated. The filing does not provide figures for any of those outcomes.
What the filing leaves open
The disclosure does not specify an execution deadline, project location, voltage level or capacity. It also does not set out payment milestones, an advance amount, a margin estimate or the period over which revenue may be recognised. Those details should not be filled in from the general description of transmission work.
The useful next disclosures would be a more detailed contract update, execution schedule or progress report. Until then, the supported reading is a Rs22.05 crore pre-GST LOI covering supplies, erection and civil works, not a completed infrastructure project or a forecast of earnings.
Source: Leapfrog Engineering Services’ November 21, 2026 exchange disclosure.