SRM’s Rs111.16 crore NHAI contract: 18 months from an unstated appointed date

Original conceptual highway grade-separator construction illustration. SRM Contractors: Rs111.16 crore NHAI contract in Gujarat; 18 months from the appointed date, which the filing does not state.

SRM Contractors has reported a Rs111.16 crore contract from the National Highways Authority of India for work on the Porbandar-Jetpur section of NH-27 in Gujarat. Its November 26 disclosure describes an awarded contract, rather than an L1 bid position awaiting an award.

The execution clock needs a separate label. The company says the work is to be completed within 18 months from the appointed date. The filing does not identify that date, so it does not support counting 18 months from the announcement or publishing a fixed completion month.

What the contract covers

Annexure A describes the construction of grade separators at Rabarika Chowkdi, Kutiyana Bypass near village Mal Choliyana and Kutiyana village, together with a 2.20 km service road on the Porbandar-Jetpur stretch of NH-27. The awarding entity is NHAI and the contract is domestic.

The 2.20 km measurement belongs to the service road in the disclosed scope. It should not be stretched into the total length of the highway section, the combined length of every grade separator, or a claim that SRM is building a new 2.20 km national highway.

The cover letter and annexure both state a contract value of Rs111.16 crore. The disclosure does not specify whether that amount includes GST. Adding a tax assumption, or describing it as a tax-exclusive value, would go beyond the document.

Why the appointed date matters

The announced duration has a trigger: the appointed date. A disclosure date tells readers when the company informed the exchanges. It is not evidence that the contractual execution period began on that same day.

Without a stated appointed date, the defensible timetable remains exactly the one disclosed: 18 months from that date. The filing also does not provide a mobilisation schedule, construction milestones or a month-by-month revenue profile.

This distinction matters when tracking delivery. A later update identifying the appointed date would help establish the starting point for the 18-month period. It would still be necessary to check subsequent progress rather than treating the original duration as proof of completion.

An award is not collected revenue

SRM says it has bagged the contract and uses awarded-contract language in the annexure. That is firmer than a lowest-bidder announcement. It is still different from completed construction, certified billing or cash received.

The disclosed Rs111.16 crore is the contract size, not a profit forecast or a statement of immediate revenue. The filing gives no project margin, customer advance, payment schedule or working-capital requirement. It therefore does not support calculating earnings or assuming that the entire amount will be recognised in one financial period.

There is also no consolidated order-book reconciliation in this document. Readers cannot use the contract value alone to calculate SRM’s net order-book increase after execution and other changes, or to infer its total outstanding work.

What the relationship disclosures say

The company answers no to promoter or promoter-group interest in the entity awarding the contract. It also answers no to whether the contract is a related-party transaction. Those are the company’s disclosures in Annexure A, not a separate assurance about project returns or collection timing.

The next useful facts would be the appointed date, execution updates and financial disclosures connecting construction progress with revenue and cash. Until then, keep the three labels separate: an awarded Rs111.16 crore contract, the specified Gujarat work scope, and an 18-month period tied to an unstated appointed date.

Source

SRM Contractors’ full November 26, 2026 exchange disclosure, including Annexure A. The article is based on the complete contract disclosure, with no live share-price claim.

Disclaimer

This article is for information and education only and is based on public sources. Please double-check the original source before making any financial decision. We hold no shares in the companies mentioned. Our purpose is to promote financial literacy and resources, without any personal or monetary motive. We have never taken or built trading or investing positions to spread false price information for personal gain. We have not used, and will not use, this platform to mislead any trader or investor. This is not investment advice.

Educational news and context only. This is not a buy or sell recommendation. Market investments carry risk.
Wolf of Dalal Streetwolfofdalalstreet.com BizTechIndiabiztechindia.com
WOLF OF INDIA
Jobat360jobat360.com Trending on Nettrendingonnet.com Stockmarket360stockmarket360.in

Keep Stockmarket360 handy

On Android or desktop, use your browser's Install app or Add to Home screen option if offered. On iPhone, open this site in Safari, tap Share, then Add to Home Screen.

This is a web app, not an App Store or Play Store download. An internet connection is needed for fresh news.